Wood Village NE Halsey Street Sewer Capacity Upgrade

Wood Village, OR

Details

$200,000

Under Budget

Project

Century West provided engineering design and construction management services for this City of Wood Village sanitary sewer improvement project. The project included replacing approximately 2,000LF of 8-inch concrete sanitary sewer within NE Halsey Street with new 12-inch HDPE sewer pipe using pipe bursting methods. Century West oversaw the production of the plans and specifications while also working closely with the client and sub-consultants. The City budgeted over $700,000 for this project based on cost estimating completed as part of the City’s Sewer Master Plan, however, Century West was able to deliver the project for the City for just over $500,000.